Meaning. The discharge of a contract when a later event makes performance impossible or unlawful.

Section 56 of the Indian Contract Act provides that a contract to do an act which, after it is made, becomes impossible or unlawful through an event the promisor could not prevent, becomes void when the act becomes impossible or unlawful. The second paragraph is the statutory basis of frustration in India.

In Satyabrata Ghose (1953) the Supreme Court held that “impossible” is not used in a literal sense: performance becomes impossible when an untoward event upsets the very foundation of the contract and makes it useless for its object. The Court also held that s.56 is a positive rule, so Indian courts need not rely on the English theory of an implied term. Frustration must not be self-induced, and mere hardship or higher cost does not frustrate a contract. Money paid can be recovered under s.65.

Example

When the hall booked for a wedding was destroyed by fire, the contract was discharged by frustration under s.56 and the advance was refundable under s.65.

In Indian law

See also

force majeure · lex non cogit ad impossibilia · void agreement · restitution