Examination, notice and acceptance; the buyer's rights to reject documents and goods, fundamental breach, avoidance, cure and price reduction under the CISG and the Sale of Goods Act; the rights of the unpaid seller (lien, stoppage in transit, resale); and frustration and force majeure in international contracts, from Taylor v. Caldwell to the Suez cases, Satyabrata Ghose and Energy Watchdog.

On this page
  1. 1. Examination and notice
  2. 2. Two rights of rejection in documentary sales
  3. 3. Rejection and the buyer's remedies under the CISG
  4. 4. The unpaid seller
  5. 5. Frustration: the common law
  6. 6. Frustration in Indian law: section 56
  7. 7. Force majeure and the CISG
  8. How this is examined
Cases checked to exist. Read the judgment before quoting a holding.

Every case cited here has been checked to exist — the citation resolves and names the right parties. The propositions attributed to each case have not been verified line by line against the judgment. Case names link through to the full judgment: read it before quoting a holding in an examination answer, and never carry a proposition from notes into court on trust.

The examinable core. February 2025 set two essays from this cluster: “rules relating to rejection of goods in contracts under international sale of goods” and “What is frustration of contract? Under what circumstances is the contract frustrated?”. August 2024 asked for the rights of the unpaid seller and a short note on frustration. Rejection depends on two ideas: the buyer must examine and give notice in time, and only a serious breach justifies throwing the goods back.

1. Examination and notice

Under the CISG the buyer must examine the goods within as short a period as is practicable; where carriage is involved, examination may be deferred until arrival (Article 38). He loses the right to rely on a lack of conformity unless he gives the seller notice specifying its nature within a reasonable time after he discovered or ought to have discovered it, and in any event within two years of actual delivery unless a contractual guarantee provides otherwise (Article 39). The seller cannot rely on these rules if the defect relates to facts he knew and did not disclose (Article 40).

The Sale of Goods Act, 1930 gives the buyer a reasonable opportunity of examining the goods (section 41). The buyer is deemed to have accepted the goods (section 42) when he intimates acceptance to the seller, does an act inconsistent with the seller's ownership, or retains the goods beyond a reasonable time without intimating rejection. Once he has accepted, he can only claim damages for breach of warranty. A buyer who rightfully rejects need not return the goods; it is enough to tell the seller he refuses them (section 43).

2. Two rights of rejection in documentary sales

In a CIF or similar contract the buyer has a right to reject non-conforming documents on tender, and a separate right to reject non-conforming goods on arrival. Accepting the documents does not waive the right to reject the goods for a defect not apparent on the documents. But if the buyer accepts documents that show a defect (a late shipment date on the bill of lading), he cannot later reject on that ground: Kwei Tek Chao v. British Traders and Shippers Ltd. (1954).

3. Rejection and the buyer's remedies under the CISG

The CISG thus prefers keeping the contract alive: cure and price reduction come before avoidance. The Sale of Goods Act, by contrast, lets the buyer reject for breach of any condition, such as correspondence with description (section 15) or merchantable quality (section 16(2)), however slight, subject to acceptance under section 42.

4. The unpaid seller

A seller is unpaid when the whole price has not been paid or tendered, or when a bill of exchange taken as conditional payment has been dishonoured (Sale of Goods Act, section 45). His rights against the goods (section 46) are:

The CISG equivalents: the seller may require payment (Article 62), fix an additional period (Article 63), avoid for fundamental breach (Article 64), and recover damages. Under Article 71 a party may suspend performance if it becomes apparent that the other will not perform a substantial part, and Article 71(2) lets a seller who has dispatched the goods prevent their handing over to the buyer, even if the buyer holds a document entitling him to them. Article 72 deals with anticipatory breach.

5. Frustration: the common law

A contract is frustrated when, without the fault of either party, a supervening event makes performance impossible, or so radically different from what was undertaken that to hold the parties to it would be to make a new contract. Both are then discharged.

6. Frustration in Indian law: section 56

Section 56 of the Indian Contract Act, 1872 makes void an agreement to do an act impossible in itself, and a contract which becomes impossible or, by reason of some event the promisor could not prevent, unlawful after it is made. In Satyabrata Ghose v. Mugneeram Bangur & Co., 1953 INSC 71, AIR 1954 SC 44, the Supreme Court held that the doctrine of frustration falls within section 56; “impossible” is not confined to physical impossibility but includes impracticability in the sense of the object being defeated. Requisition of the land for war purposes did not frustrate a contract to develop plots, because the contract contemplated delay and the requisition was temporary.

In Energy Watchdog v. Central Electricity Regulatory Commission, 2017 INSC 338, (2017) 14 SCC 80, power generators said that an Indonesian law raising the export price of coal had frustrated their long-term supply agreements. The Court held that a rise in the cost of performance, even a steep one, is neither frustration nor force majeure where the contract did not make a particular source of coal or price its foundation. Where a contract contains a force majeure clause, the matter is governed by the contract (section 32), not by section 56.

7. Force majeure and the CISG

International contracts usually contain a force majeure clause listing events (war, embargo, natural disaster, epidemic, government action) and providing for suspension and then termination, often modelled on the ICC Force Majeure Clause. Under Article 79 of the CISG a party is not liable in damages for a failure due to an impediment beyond its control that it could not reasonably have taken into account at the time of contracting or avoided or overcome. The exemption lasts only while the impediment lasts, notice must be given, and it bars only damages; the other party's other remedies, including avoidance, remain (Article 79(5)).

Trap. Market changes, currency movements and price rises do not frustrate a contract. Write Tsakiroglou for international sales and Energy Watchdog for Indian law. Closure of a route, embargo or export ban is a stronger case, but only if performance in the contemplated way is the foundation of the contract.

How this is examined

For rejection: examination and notice (Articles 38 and 39; sections 41 and 42), the two rights of rejection in CIF sales, fundamental breach and avoidance, cure and price reduction, and preservation of goods. For frustration: definition, the English cases, section 56 with Satyabrata Ghose, the circumstances that do and do not frustrate, and force majeure under Article 79. For the unpaid seller: section 45, then lien, stoppage in transit and resale, with the CISG Article 71(2) parallel.