KSLU Corner™ New AIBE previous QP

Notification and acquisition: preliminary notification, objections and declaration

Land Law · Unit I · Topic 2 of 18 · 7 min read

The steps from the section 11 preliminary notification to the section 19 declaration under the 2013 Act: publication, the bar on transactions, survey, objections within sixty days, the Rehabilitation and Resettlement Scheme, and the twelve-month time limits.

On this page
  1. 1. The preliminary notification: section 11
  2. 2. Survey and damage: sections 12 and 13
  3. 3. Objections: section 15
  4. 4. The Rehabilitation and Resettlement Scheme: sections 16 to 18
  5. 5. The declaration: section 19
  6. 6. After the declaration: sections 20 to 22
  7. How this is examined
Cases checked to exist. Read the judgment before quoting a holding.

Every case cited here has been checked to exist — the citation resolves and names the right parties. The propositions attributed to each case have not been verified line by line against the judgment. Case names link through to the full judgment: read it before quoting a holding in an examination answer, and never carry a proposition from notes into court on trust.

The examinable core. “Notification and acquisition” is a sequence, and the marks go to getting the sequence and the time limits right: SIA → preliminary notification (s.11) → survey (s.12) → objections within 60 days (s.15) → R&R Scheme (ss.16–18) → declaration within 12 months (s.19) → notice to persons interested (s.21) → award within 12 months (s.25). This note covers the steps up to section 22; the award, possession and lapse are in the next note.

1. The preliminary notification: section 11

Whenever it appears to the appropriate Government that land in any area is required or likely to be required for a public purpose, it issues a preliminary notification with details of the land. Section 11(1) requires publication in five ways:

Immediately afterwards the Gram Sabha (or municipality, or the Autonomous Council in Sixth Schedule areas) must be informed of its contents at a meeting called for the purpose (section 11(2)). The notification must state the nature of the public purpose, the reasons for displacement, a summary of the SIA report and the particulars of the Administrator for rehabilitation and resettlement (section 11(3)).

Two consequences follow from publication.

The date of the section 11 notification also fixes the date for determining market value (proviso to section 26(1)), which is why the notification matters in every compensation dispute.

2. Survey and damage: sections 12 and 13

Section 12 authorises officers to enter and survey the land, take levels, dig or bore into the sub-soil, set out boundaries and mark them, and if necessary cut standing crops, fences or jungle. Three safeguards apply:

Under section 13 the officer must pay or tender payment for any damage caused at the time of entry. A dispute about the amount goes to the Collector, whose decision is final.

3. Objections: section 15

Any person interested in the notified land may object within sixty days of the preliminary notification to:

Objections are made in writing to the Collector, who must hear the objector in person, through an authorised person or through an advocate. After any further inquiry he reports to the Government with his recommendations, the record of proceedings, the approximate cost of acquisition and the number of affected families likely to be resettled. The Government’s decision on the objections is final (section 15(3)), subject to judicial review.

The hearing is a real one. A decision that ignores objections, or a report written without hearing the objector, is open to challenge under Article 226 for breach of the right to be heard, which Kolkata Municipal Corporation v. Bimal Kumar Shah, 2024 INSC 435, treats as one of the procedural sub-rights inside Article 300A.

4. The Rehabilitation and Resettlement Scheme: sections 16 to 18

While objections are being heard, the rehabilitation track runs in parallel. On publication of the preliminary notification the Administrator conducts a survey and census of affected families (section 16(1)), prepares a draft R&R Scheme with each family’s entitlements and a time limit for implementation, publicises it, discusses it in the Gram Sabhas and holds a public hearing (section 16(2) to (5)). The Collector reviews the draft with the project-level R&R Committee and sends it to the Commissioner for approval (section 17). The approved Scheme is published (section 18). The detail is in the Unit I note on the R&R award.

5. The declaration: section 19

When the Government is satisfied, after considering the Collector’s report under section 15(2), that particular land is needed for a public purpose, a declaration is made under the hand and seal of a Secretary (or other authorised officer). Along with it, the Government declares the resettlement area. Different declarations may be made for different parcels covered by one preliminary notification.

Three conditions precede the declaration:

The declaration is published in the same five ways as the preliminary notification (section 19(4)) and must state the district, the purpose, the approximate area and where a plan may be inspected (section 19(5)). Under section 19(6) it is conclusive evidence that the land is required for a public purpose.

Time limit (section 19(7)). If no declaration is made within twelve months of the preliminary notification, the notification is deemed to be rescinded. Periods during which the proceedings were held up by a court stay or injunction are excluded, and the Government may extend the period by a written decision that is notified and uploaded.

Trap. “Conclusive evidence” in section 19(6) does not put the declaration beyond review. A declaration made without the R&R summary, without the deposit, or after the twelve-month period has run is not a declaration the Act recognises, and a colourable or mala fide “public purpose” can still be struck down under Article 226.

6. After the declaration: sections 20 to 22

The inquiry and award under section 23 then follow.

How this is examined

“Discuss the provisions relating to notification and acquisition” was the first essay in June 2025. Answer in the order of this note and give every time limit: six months for the SIA, sixty days for objections, twelve months for the declaration, thirty days to six months for the section 21 hearing, and twelve months for the award. “Preliminary notification” was a 6-mark short note in January 2026: write section 11(1) to (5), the market-value date, and section 19(7).