Compensation for breach under section 73 and the rule in Hadley v Baxendale, the kinds of damages, liquidated damages and penalties under section 74 from Fateh Chand to Kailash Nath, the duty to mitigate, and section 75.

On this page
  1. 1. Section 73: the rule
  2. 2. Hadley v. Baxendale: the two limbs
  3. 3. Kinds of damages
  4. 4. Section 74: liquidated damages and penalty
  5. 5. Duty to mitigate
  6. 6. Ascertainment of damages
  7. 7. Section 75
  8. 8. Problem
  9. How this is examined
Cases checked to exist. Read the judgment before quoting a holding.

Every case cited here has been checked to exist — the citation resolves and names the right parties. The propositions attributed to each case have not been verified line by line against the judgment. Case names link through to the full judgment: read it before quoting a holding in an examination answer, and never carry a proposition from notes into court on trust.

Two sections do most of the work. Section 73 decides which losses can be recovered (remoteness) and how they are measured. Section 74 deals with the case where the parties have named a sum in advance. Keep the two apart in your answer; examiners mark down essays that blur unliquidated and liquidated damages.

1. Section 73: the rule

When a contract has been broken, the party who suffers by the breach is entitled to receive, from the party who has broken it, compensation for any loss or damage caused to him by the breach which:

Such compensation is not to be given for any remote and indirect loss or damage sustained by reason of the breach. The second paragraph applies the same rule to failure to discharge an obligation resembling one created by contract (the quasi-contracts in sections 68 to 72).

The Explanation provides that, in estimating the loss or damage, the means which existed of remedying the inconvenience caused by the non-performance must be taken into account. This is the statutory basis of the duty to mitigate.

The first illustration states the usual measure in sale of goods: A contracts to sell and deliver 50 maunds of saltpetre to B at a certain price, to be paid on delivery. A breaks his promise. B is entitled to receive from A, by way of compensation, the sum, if any, by which the contract price falls short of the price for which B might have obtained 50 maunds of saltpetre of like quality at the time when it ought to have been delivered.

2. Hadley v. Baxendale: the two limbs

In Hadley v. Baxendale (1854) the crankshaft of the plaintiffs' mill broke. They gave it to a carrier to take to the engineers at Greenwich as a pattern for a new one. The carrier delayed delivery, and the mill stood idle for several extra days. The plaintiffs claimed their lost profits. Alderson B. held the loss too remote and stated the rule that section 73 reproduces:

The carrier was not told that the mill would stop without the shaft. In the usual course a miller might well have a spare shaft, so the loss of profits did not arise naturally, and the special circumstance had not been communicated.

In Victoria Laundry v. Newman Industries (1949) the delivery of a boiler to a laundry was delayed by five months. The laundry recovered the ordinary profits it would have made from expanding its business, because the sellers, as engineers, knew it was needed for immediate use. It could not recover the profits from exceptionally lucrative dyeing contracts with the Ministry of Supply, of which the sellers knew nothing. Asquith L.J. restated the test as what was reasonably foreseeable as liable to result, in the light of the knowledge actually possessed. The Heron II (Koufos v. Czarnikow, 1969) later said that in contract the loss must be “not unlikely” to result, a stricter test than in tort.

3. Kinds of damages

4. Section 74: liquidated damages and penalty

Section 74 provides that when a contract has been broken, if a sum is named in the contract as the amount to be paid in case of breach, or if the contract contains any other stipulation by way of penalty, the party complaining of the breach is entitled, whether or not actual damage or loss is proved to have been caused, to receive from the party in breach reasonable compensation not exceeding the amount so named or the penalty stipulated.

English law distinguishes a genuine pre-estimate of loss (enforced in full) from a penalty (not enforced). Section 74 cuts across that distinction.

Trap. “Whether or not actual damage is proved” in section 74 does not mean that loss is irrelevant. After Kailash Nath, the words relieve the plaintiff only of strict proof of the amount where loss is hard to quantify. Where it is clear that no loss at all was suffered, nothing is payable, whatever the clause says.

5. Duty to mitigate

The Explanation to section 73 requires the injured party to take reasonable steps to reduce his loss. He cannot recover loss he could have avoided. In Murlidhar Chiranjilal v. Harishchandra Dwarkadas, 1961 INSC 125, AIR 1962 SC 366, the Supreme Court held that the Explanation and the first illustration to section 73 embody the principle that the plaintiff must take reasonable steps to mitigate, and that a buyer of goods ordinarily recovers the difference between the contract price and the market price on the date of breach, because he could have bought in the market then. The duty is only to act reasonably; he need not take risky or extraordinary steps, and the burden of proving failure to mitigate is on the defendant.

6. Ascertainment of damages

7. Section 75

A person who rightfully rescinds a contract is entitled to compensation for any damage he has sustained through the non-fulfilment of the contract. Rescission and damages are not alternatives. The illustration: A, a singer, contracts with B, the manager of a theatre, to sing at his theatre two nights a week for two months at Rs 100 a night. On the sixth night A wilfully absents herself, and B in consequence rescinds the contract. B is entitled to claim compensation for the damage he has sustained through the non-fulfilment of the contract. (These are the facts of the first illustration to section 39, carried one step further.)

8. Problem

A contracts to supply a generator to B's cold storage by 1 April. A is not told that B has already contracted to store a merchant's mangoes from 1 April. The generator arrives on 20 April; the mangoes, kept without power, rot. B claims (i) the profit he would have earned on the cold storage in April and (ii) the Rs 5 lakh he paid the merchant for the rotten mangoes.

Issue. Which of B's losses are recoverable under section 73.

Law. Section 73 and Hadley v. Baxendale: losses arising naturally, and losses within the contemplation of both parties at the date of contract. Victoria Laundry separates ordinary profits from special contracts.

Application. A supplier of a generator to a cold storage knows it is needed to run the business, so the ordinary loss of use for April arises naturally from the delay (first limb). The liability to the merchant flows from a particular contract that A was not told about; it falls under the second limb, and the condition of communication is not met. B was also bound to mitigate, for example by hiring a generator if one was reasonably available.

Conclusion. B recovers the ordinary loss of April's use (reduced by what he could reasonably have saved), but not the Rs 5 lakh paid to the merchant.

How this is examined

As a 10-mark essay: “Explain the rules regarding damages for breach of contract” or “Explain the rule in Hadley v. Baxendale”. Cover section 73, both limbs, Victoria Laundry, kinds of damages, mitigation and section 74. As a short note: liquidated damages and penalty (with Fateh Chand and Kailash Nath), nominal damages, or the duty to mitigate. Remoteness problems like the one above are common in Part C.

Now try the real questions: Contract I past question papers.